The Ariba 9r2 Upgrade Implementation project team has been hard at work these past couple of months testing to ensure a smooth transition to this new version. Upgrading to 9r2 ensures that our Ariba platform is up to date. The upgrade has been completed and servers were back up during the Labor Day holiday.

 

What's new in Ariba release 9r2?

whats new types
Expires Date

How do I cancel a requisition?

Only the Requisition Requester who initiated the RQ can cancel it. If that person is not available, send a ticket to PCS Help via UW Connect.

In the requisition, click on Related Actions:

  • Select Requisition
  • Select Cancel

 

  • The current date can be entered as the "Accounting Date"
  • Add a reason for the cancelation in the "Comments" box.
  • Click "Ok"

If incorrect related worktags on a Grant Driver worktag are used on POs and SIs, how can I correct them?

Due to ongoing beginning balance reconciliation efforts and preparation for fiscal year end close, any reclass journals intended to move between cost centers within one grant will be deferred until FY25. Since transactions will continue to post journals with the original Grant worktags on Purchase Orders, this should be considered when performing spend & budget analysis. Units may continue to perform payroll accounting adjustments (PAAs) and Accounting Adjustment.

What related worktags for Grant Driver worktags need to match with POs and SIs? What worktags don’t need to match?

Only Balancing Unit, Fund, Function, and Resource worktags need to match between the existing Grant Driver worktag and POs and SIs. All other related worktags on the Grant Driver worktag do not need to match for approval to occur and payment to process. 

What happens to existing Purchase Orders (POs) and Supplier Invoices (SIs) after a change is made to a related worktag on a Grant Driver worktag?

All existing POs and SIs will be processed and paid according to the original worktags on the PO. Run R1514 - Purchase Order Lifecycle to review existing POs and SIs. Any new PO will use the updated related worktags. BEFORE submitting a new requisition, verify the grant wortags are correct.